SCH Number 2019079088
Project Info
- Title
- San Gabriel Valley Water Company Plant B14 Project
- Description
- San Gabriel Valley Water Company- El Monte (SGVWC) proposes to construct a second reservoir at the existing Plant Bl 4 site to allow SGVWC operational flexibility to store additional water supplied from Plant Bl 2 during periods of low demand. The second reservoir will also allow for the existing reservoir to be taken out of service when required for routine maintenance. The existing Plant Bl 4 facility is located within an approximately 4.02-acre site, and it currently consists of one 1.19 million gallon buried concrete reservoir, four booster pumps with a total pumping capacity of 4,000 gallons per minute, an emergency generator and electronic control equipment.
2 documents in project