Sump Station Facilities Improvements Project
7 Documents in Project
Summary
SCH Number
2021030186
Lead Agency
City of Sacramento
Document Title
Sump Station Facilities Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
8/19/2021
Document Description
The project consists of five existing sump stations within the City of Sacramento: Sumps 089,151, 155, 058, and 102. The sump stations direct treated storm water through underground piping to storm water outfalls along waterways within the City. As mandated by the Sacramento Area Flood Control Agency (SAFCA) and the U.S.
Army Corps of Engineers (USA CE), sump station outfalls that penetrate and cross major levees within the City of Sacramento are inspected on a five-year cycle. The project entails the complete replacement of the pump discharge pipe for three drainage sump station facilities (Sumps 089, 151, and 155) and installation of stairs on the waterside slope for two additional drainage sump station facilities (Sumps 058 and 102). The improvements would not alter the overall capacity of the sump station facilities relative to existing conditions.
Contact Information
Name
Scott Johnson
Agency Name
City of Sacramento
Contact Types
Lead/Public Agency
Phone
Name
Adam Lau
Agency Name
City of Sacramento
Contact Types
Project Applicant
Phone
Location
Cities
Sacramento
Counties
Sacramento
Regions
Citywide
Cross Streets
Citywide
Notice of Determination
Approving Agency
City of Sacramento
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
www.cityofsacramento.org/Community-Development/Planning/Environmental/Impact-Reports
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes