Adopt the Mitigated Negative Declaration, Establish and Transfer Appropriations, Advertise and Award a Construction Contract for Mapleview Street Green Streets
3 Documents in Project
Summary
SCH Number
2020070430
Lead Agency
San Diego County
Document Title
Adopt the Mitigated Negative Declaration, Establish and Transfer Appropriations, Advertise and Award a Construction Contract for Mapleview Street Green Streets
Document Type
NOD - Notice of Determination
Received
Posted
5/5/2021
Document Description
The proposed project would improve storm water quality through implementation of green infrastructure, provide improved conveyance of stormwater flows, retain runoff to reduce the likelihood of flooding, create new sidewalks for pedestrian mobility and safety, and add green spaces. This action will adopt the environmental documentation, establish and transfer appropriations, and approve the advertisement and subsequent contract to the lowest responsive and responsible bidder for the Mapleview Street Green Streets Project. Construction is anticipated to last approximately 6 months and is scheduled to begin fall 2021 and to be completed summer 2022.
Contact Information
Name
Amanda Parra
Agency Name
County of San Diego Project Manager
Contact Types
Lead/Public Agency
Phone
Location
Cities
Lakeside
Counties
San Diego
Regions
Unincorporated
Cross Streets
Mapleview Street from Vine Street to Pino Drive
Notice of Determination
Approving Agency
Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
County of San Diego, Department of Public Works, Environmental Services Unit, 5510 Overland Avenue, Suite 410, San Diego, California
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A