Former Naval Petroleum Reserve No. 1: Remediation of Areas of Concern
15 Documents in Project
Summary
SCH Number
2017012006
Lead Agency
California Department of Toxic Substances Control
(DTSC)
Document Title
Former Naval Petroleum Reserve No. 1: Remediation of Areas of Concern
Document Type
NOD - Notice of Determination
Received
Posted
6/21/2024
Document Description
The Department of Toxic Substances Control (DTSC) approved the Remedy Selection and Statement of Basis (RSSB) Work Plans for Areas of Concern (AOC) 044-003, AOC 044-004, and AOC 044-005, and AOC 052, a Draft Interim Measures/Removal Action Work Plan (IM/RAW) for AOC 029, Explanations of Significant Differences (ESDs) and associated Amendments to Final Remedy Selection and Statement of Basis (RSSB) Work Plans for AOC 030-001 and AOC 072, Addendums to the Final Interim Measure (IM)/Removal Action Workplans (RAWs) for AOC 012-004, 082-002, 119-005 and 119-018 and Proposed Corrective Action Management Unit (CAMU) designation for Area of Concern (AOC) 030-001.
Contact Information
Name
Ryan Mitchum
Agency Name
Department of Toxic Substances Control
Job Title
Project Manager
Contact Types
Lead/Public Agency
Phone
Email
Location
Cities
Bakersfield
Counties
Kern
Regions
Southern California
Zip
93276
Other Location Info
28590 Highway 119, northwest of Highway 119 and approximately 25 miles southwest of Bakersfield, California
Notice of Determination
Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On
County Clerk
Kern
Final Environmental Document Available at
www.envirostor.dtsc.ca.gov/public/
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes