The Culver Studios Comprehensive Plan Amendment No. 7
4 Documents in Project
Summary
SCH Number
2016111044
Lead Agency
City of Culver City
Document Title
The Culver Studios Comprehensive Plan Amendment No. 7
Document Type
NOD - Notice of Determination
Received
Posted
1/10/2018
Present Land Use
GPD: Studio
Culver City Zoning Code: S Zoning District (Studio)
Document Description
Project, which is reflected in the proposed Comprehensive Plan Amendment No. 7 would technologically update and expand the facilities within the Project Site. No major exterior changes are proposed to the Mansion or adjacent Buildings D, E, H, and I. The project would modernize and expand the Central Area of the Project Site for a net new sq. footage of approx. 345,007 sf. The Project would also include two new parking structures, the Central Parking Structure (836 spaces) and the Van Buren Parking Structure (1,109 spaces). Construction is anticipated to start in the first quarter of 2018 and is anticipated to be completed mid 2020.
Contact Information
Name
Michael Allen
Agency Name
Culver City
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Culver City
Counties
Los Angeles
Cross Streets
Southern side of intersection between Ince Blvd and Washington Blvd
Zip
90232
Total Acres
14.3
Parcel #
4206-022-002
State Highways
I-10, I-405, SR-187
Railways
Metro Expo Line
Schools
Over 10
Waterways
Ballona Creek
Notice of Determination
Approving Agency
City Council
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.