Peninsula Corridor Electrification Project (PCEP) as Modified (Power lnterconnection)
12 Documents in Project
Summary
SCH Number
2013012079
Lead Agency
Peninsula Corridor Joint Powers Board
Document Title
Peninsula Corridor Electrification Project (PCEP) as Modified (Power lnterconnection)
Document Type
NOD - Notice of Determination
Received
Posted
3/25/2020
Document Description
In 2015, the JPB certified the PCEP Final EIR. Since then, the design for the electrical interconnection from PG&E substations in South San Francisco and San Jose to the JPS substations has been revised. The JPS prepared an Addendum that found that the refined design would not result in any new or substantially more severe environmental impacts than disclosed in the Final EIR.
Contact Information
Name
Stacy Cocke
Agency Name
Peninsula Corridor Joint Powers Board
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Peninsula Corridor Joint Powers Board
Contact Types
Project Applicant
Location
Cities
San Jose, South San Francisco
Counties
San Mateo, Santa Clara
Notice of Determination
Approving Agency
Peninsula Corridor Joint Powers Board
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes