Camarillo Airport Water System Improvements - Phase 3
2 Documents in Project
Summary
SCH Number
2012061021
Lead Agency
City of Camarillo
Document Title
Camarillo Airport Water System Improvements - Phase 3
Document Type
NOD - Notice of Determination
Received
Posted
9/6/2012
Present Land Use
Light Manufacturing
Document Description
Installation of 1, 9000 feet of 16-inch portable water pipeline (HDPE) within the Camarillo Airport property. Construction methods to be used: horizontal direction drilling.
Contact Information
Name
Lucia McGovern
Agency Name
City of Camarillo, Dept. of Public Works
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Camarillo
Counties
Ventura
Cross Streets
Wood Road/Aviation Way
Zip
93010
Total Acres
1
Parcel #
230017013
State Highways
SR-101
Airports
Camarillo
Schools
Pleasant Valley/Oxnard
Waterways
Camarillo Hills Drain - Revelon Slough
Notice of Determination
Approving Agency
City Council for the City of Camarillo
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes