Fay Hill Pumping Plant Replacement and Pipeline Improvements - Addendum to the Water Treatment and Transmission Improvements Program (WTTIP) Environmental...
16 Documents in Project
Summary
SCH Number
2005092019
Lead Agency
East Bay Municipal Utility District
(EBMUD)
Document Title
Fay Hill Pumping Plant Replacement and Pipeline Improvements - Addendum to the Water Treatment and Transmission Improvements Program (WTTIP) Environmental...
Document Type
NOD - Notice of Determination
Received
Posted
12/18/2019
Document Description
The Fay Hill Pumping Plant (PP) and Pipeline Improvements Project (Project) is one of many projects in the certified WTTIP EIR and includes replacement of the pump units at the Fay Hill PP with larger units and replacement of about 500 feet of existing pipeline. During the detailed design, some changes and additions to the original Project were identified. These changes include full replacement of the Fay Hill PP at EBMUD's existing Rheem PP site, installation of additional suction and discharge pipelines, and demolition of the existing Fay Hill PP.
In accordance with the California Environmental Quality Act, EBMUD completed an Addendum to the WTTIP EIR to address environmental impacts from the design changes. An evaluation was conducted and it was determined that the changes do not result in new significant impacts or cause an increase in the severity of previously identified impacts as presented in the certified WTTIP EIR. EBMUD will implement the same mitigation measures for the design changes that are presented in the WTTIP EIR. No further environmental documentation is required .
Contact Information
Name
Timothy McGowan
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Moraga
Counties
Contra Costa
Parcel #
255-030-026 and 255-150-009
Notice of Determination
Approving Agency
East Bay Municipal Utility District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes