Bickford Ranch/Antelope Canal PLX 1816
2 Documents in Project
Summary
SCH Number
2000122035
Lead Agency
Placer County Water Agency
Document Title
Bickford Ranch/Antelope Canal PLX 1816
Document Type
NOD - Notice of Determination
Received
Posted
3/22/2001
Present Land Use
Mixed Use Specific Plan Area/F (Farm) with 1- and 20-acre minimum parcel sizes
Document Description
The project will construct improvements to the existing Antelope Canal/Clover Valley Reservoir raw water conveyance system to deliver water to the proposed new Bickford Ranch Reservior, with pipelines to and around the existing Clover Valley Reservoir (CVR) to have the ability to bypass either or both reservoirs. The existing canal will be extended approximately 200 feet and water diverted into a new inlet structure to convey the water through an enclosed inflow pipeline along the slope, under the Union Pacifice Railroad line, and then extending in an easterly direction across Clover Valley Creek to discharge into the new Bickford Ranch Reservoir. The new Bickford Ranch Reservior will have a height of sixteen (16) feet with an approximate storage capacity of 11 acre feet. An outflow pipeline from the Bickford Ranch Reservior will extend westerly (parrallel to a portion of the inflow line) to and around the existing CVR to the reservoir outlet works. The upper end (approximately 200 lineal feet) of the eroded canal will be back filled with approximately 5,000 cubic yards of earth fill and rip rap to form a solid base for construction of the new pipeline diversion structure.
Contact Information
Name
Ken Powers
Agency Name
Placer County Water Agency
Contact Types
Lead/Public Agency
Address
Phone
Location
Cities
Auburn, Lincoln, Loomis
Counties
Placer
Cross Streets
Sierra College Boulevard/English Colony Way
Parcel #
031-190-05; 031-200-01
State Highways
I-80
Railways
UPRR
Township
12N
Range
7E
Section
22
Notice of Determination
Approving Agency
Placer County Water Agency
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No