513 North Main Street Building Demolition

2 Documents in Project

Summary

SCH Number
2000121018
Lead Agency
Los Angeles County
Document Title
513 North Main Street Building Demolition
Document Type
NOD - Notice of Determination
Received
Posted
3/9/2001
Present Land Use
The 513 North Main Street building is an abandoned building located near the El Pueblo Los Angeles Historic Monument. The lot is zoned a [T][Q]C4-2D. This zoning classifications allows commercial uses consistent with Height District No. 2 development standards and special development restrictions.
Document Description
The 513 North Main Street building, constructed in 1918, does not meet current building codes and it is deteriorating to the point of being unsafe. Accordingly, the Los Angeles County Department of Public Works is proposing to demolish the abandoned five-story building. Demolition activities would require approximately 10 to 13 weeks to complete. Upon completion of the demolition activities, the site would be converted to an open paved lot. The building is not listed on the National Register of Historic places because of its late date and lack of historical association with the surrounding buildings. Several nearby buildings are listed on the National Register.

Contact Information

Name
David MacGregor
Agency Name
Los Angeles County Department of Public Works
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles, Los Angeles, City of
Counties
Los Angeles
Cross Streets
Republic Street/New High Street
Total Acres
less than 1
Jobs
30
Parcel #
5408-007-904
State Highways
Harbor Freeway (Hwy 101)
Railways
Union Station
Waterways
Los Angeles River

Notice of Determination

Approving Agency
Los Angeles County Department of Public Works
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print