Concurrence in the Issuance of a Solid Waste Facility Permit for West Valley Material Recovery Facility, San Bernardino County (SWIS No. 36-AA-0341)

6 Documents in Project

Summary

SCH Number
1992052019
Lead Agency
San Bernardino County
Document Title
Concurrence in the Issuance of a Solid Waste Facility Permit for West Valley Material Recovery Facility, San Bernardino County (SWIS No. 36-AA-0341)
Document Type
NOD - Notice of Determination
Received
Posted
8/15/2007
Present Land Use
Burrtec Material Recovery Facility and Solid Waste Transfer Station 5000 tons daily Z/GP: FT/IR
Document Description
Increase traffic county from 1,718 to 1,877 vehicles per day, increase maximum daily tonnage from 5,000 to 7,500 tons per day, expansion of the Material Recovery Facility building by an additional 41,032 square feet, increase the design capacity from 5,877 tons to 8,280 tons, change the hours of operation for the public from 5:00 a.m. to 6:00 p.m. to 7:00 p.m., and correctino of the acreage section of the proposed Solid Waste Facilities Permit.

Contact Information

Name
Dianne Ohiosumua
Agency Name
California Integrated Waste Management Board
Contact Types
Lead/Public Agency

Location

Cities
Fontana
Counties
San Bernardino
Cross Streets
Napa and Etiwanda
Zip
92335
Total Acres
31.5
Parcel #
0229-291-31
State Highways
I-10, 15, and 210
Railways
BNSF and UPRR
Airports
Ontario
Schools
Fontana
Waterways
San Sevaine Flood Control Channel
Township
1S
Range
6W
Section
16
Base
SBBM

Notice of Determination

Approving Agency
California Integrated Waste Management Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA